| ROUGH OPENING SHOULD BE NOMINAL DOOR
WIDTH + INSIDE SIDELITE WIDTH + 3" AND NOMINAL HEIGHT + 3/4"
|
| 1) INSTALL DOOR FRAME
ACCORDING TO THE ECLIPSE DOOR FRAME INSTALLATION INSTRUCTIONS.
|
|
| 2) INVERT AND INSERT GLAZING
SNAP-IN AT BASE AT DOOR FRAME STRIKE JAMB. SECURE SNAP-IN TO FLOOR
WITH STEEL PINS AND TO STRIKE JAMB WITH 1/2" SELF-TAPPING PAN HEAD
SCREWS.
3) ATTACH VERTICAL GLAZING SNAP-IN TO FULL LENGTH
OF DOOR FRAME STRIKE JAMB. SECURE SNAP-IN TO JAMB USING 1/2"
SELF-TAPPING PAN HEAD SCREWS SPACED 12" O.C. |

|
| 4) PLACING GLAZING HEAD
COMPONENT ON GROUND, INSTALL CORNER CLIP ON ONE END OF RAIL USING
1/2" SELF TAPPING PAN HEAD SCREWS |

|
5) MAKE SURE "NOTCH" IN CLIP
IS SECURED TIGHTLY AGAINST HEAD RAIL COMPONENT. INSTALL
GLAZING HEAD RAIL INTO ROUGH OPENING. |
|
| 6) NOTCH END OF VERTICAL
GLAZING RAIL, AS SHOWN, AND INSTALL OVER ROUGH OPENING. |

|
| 7) SECURE VERTICAL GLAZING
RAIL SLIDING CORNER CLIP FROM HEAD COMPONENT INTO GLAZING POCKET IN
VERTICAL LEG. WITH CORNER AND GLAZING POCKETS ALINED SECURE WITH
1/2" SELF TAPPING PAN HEAD SCREWS THROUGH CLIP INTO EACH VERTICAL
LEG |

|
| 8) SNAP GLAZING SILL OVER
INVERTED RAIL AT THE BASE OF THE SIDELITE |

|
|